CONSTRUCTION INFORMATION
Montgomery County Public Schools
|
|
Elliston-Shawsville
Elementary School Project
Design Information: Design Renderings for New Elliston-Shawsville Elementary School
Construction Contract Information:
Project Team:
Additional
information about each team member firm providing services on the Elliston-Shawsville
Elementary School Project can be found on their individual websites linked
from their company names. |
MCPS
Project Team: |
|||||||||||||||||||||||
|
Dan
Berenato |
||||||||||||||||||||||||
|
Greg
Burgess |
||||||||||||||||||||||||
|
|
||||||||||||||||||||||||
|
ADMINISTRATIVE
ASSISTANTS |
||||||||||||||||||||||||
|
Millie
McPherson |
||||||||||||||||||||||||
|
Anita
Akers |
||||||||||||||||||||||||
|
Linda
Baylor |
||||||||||||||||||||||||
|
|
||||||||||||||||||||||||
The following work was performed during the month of December:
· Sitework operations continued.
· Began connecting roof drains to the storm water system.
· Continued masonry construction. Main building brick veneer operations completed.
· Completed roof framing and structural steel erection.
· Completed metal roof decking.
· Continued roofing flat and sloped roofs.
· Began installing metal roofing.
· Continued glazing windows.
· Continued interior wall construction.
· Began block fill and painting operations.
· Continued sprinkler installation.
· Continued mechanical, electrical and plumbing rough ins.
Photos:
Project Overview:
12/1
- Area D from the access road.
12/1
- Facing northwest.
12/4
- Cafeteria entrance and student drop off entrance.
12/10 -
Administration and Media center.
12/21
- The access road on Monday after the snow.
12/30
- Media, Cafeteria and Loading Dock from the access road.
12/30
- Areas D and A from the access road.
12/30
- Area A.
Structure & Skin - Structural Steel, Trusses, Decking, Roofing, Veneer:
12/1
- Area C, Metal decking installed across from the Art room.
12/1
- Area C, Welding the structural steel for the west porch.

12/4
and 12/8 - Area A, Administrative Main Entrance
12/9
- Area C, Temporary protection over metal roofing substrate.


12/21, 22
and 23 - Area B, Metal roof installation.
Interior Construction:

12/1,
12/30 - Area A, Cafeteria facing east, doorway to the kitchen area

12/10,
12/30 - Area A, Cafeteria facing west.
12/1 - Area
A, Media room.
12/10
- Area C, Art room
12/21
- Area B, Painting
Systems:
12/4 -
Area B, Mezzanine panel wiring.
12/8
- Area C, Bathroom plumbing rough in.
12/10 -
Area A, Cafeteria sprinkler piping.
12/23 -
Area E, Pulling electrical feeders for building areas.
12/30 - Area B,
Data wiring.
12/30
- Area C, Ductwork rough in.
Sitework:
12/30 -
Electrical work at the sewer force main pump station.
The following work was performed during the month of November:
· Sitework operations continued.
· Continued fine grading and installing curb and gutter in the staff parking area.
· Completed main building concrete operations.
· Continued masonry construction.
· Continued roof framing and structural steel erection.
· Continued metal roof decking.
· Continued roofing flat and sloped roofs.
· Began glazing windows.
· Continued interior wall construction.
· Continued sprinkler installation.
· Continued mechanical, electrical and plumbing rough ins.
Photos:
Project Overview:
Structure & Skin - Structural Steel, Trusses, Decking, Roofing,
Veneer:
11/2 -
Area B window installation.
11/3
- Kitchen roof
11/6
-Area B metal roofing substrate.
11/9
- Area B metal roofing substrate.
11/20 -
Area D brick veneer
11/20 -
Area C, south of the art room.
Interior Construction:
11/20 -
Area A corridor bulkhead framing.
Systems:
11/3
- Roof top unit - RT-2
11/3 -
Cooling tower set.
11/10 -
Piping cooling tower.
Sitework:
11/10
- Sanitary sewer force main pump station.
The following work was performed during the month of October:
· Sitework operations continued.
· Began curb and gutter work for the parking areas.
· Continued masonry construction.
· Continued roof framing and structural steel erection.
· Continued metal roof decking.
· Continued roofing flat and sloped roofs.
· Continued interior wall construction.
· Continued sprinkler installation.
· Continued mechanical, electrical and plumbing rough ins.
Photos:
Project Overview:
Structure & Skin - Structural Steel, Trusses, Decking, Roofing, Veneer:
10/1
- Area C west porch, erecting structural steel.
10/2
- Area A, Flat roof vapor barrier
10/5
- Area D south porch, erecting structural steel.
10/8
- Area A, Admin, Roofing.
10/12
- Area A Cafeteria, Framing windows.
10/16
- Area C Art room, metal joist erection.
10/16
- Area D, Viewing down the interior of the lightweight trusses from the Area C
Mezzanine.
10/19
- Area A, Cafeteria vapor barrier
10/19 -
Area A Gymnasium, Built up roofing.
Interior Construction:
10/16
- Area A Cafeteria, Interior non-load bearing wall construction.
10/16
- Area C Mezzanine, metal stud framing.
10/20
- Area A Cafeteria, Interior non-load bearing CMU wall construction.
10/22
- Area A Cafeteria, Interior non-load bearing CMU wall construction.
10/27
- Area A Media, metal framing for bulkhead.
Systems:
10/15
- Area A Media, HVAC ductwork
10/21
- Area E Kitchen, exhaust hood.
10/22 - Area
E Kitchen, exhaust hood.
10/22
- Area E Mechanical/Electrical Room, Main electrical switch gear.
Sitework:
10/5 -
Backfilling sewer pump station.
10/7
- Distributing topsoil south of Area D.
10/12 -
Grading staff parking.
10/12 -
Curb and gutter parking area.
10/13 - Curb
and gutter parking area.
The following work was performed during the month of September:
· Sitework operations continued. Force main pump station structure was installed.
· Continued road bed construction for access road.
· Substantially completed concrete construction for the building.
· Continued masonry construction.
· Continued roof framing and structural steel erection.
· Continued metal roof decking.
· Began roofing flat and sloped roofs.
· Began interior wall construction.
· Continued sprinkler installation.
· Continued mechanical, electrical and plumbing rough ins.
Photos:
Project Overview:
9/10
- Area A, Admin and Media Center
Structure & Skin - Structural Steel, Trusses, Decking, Roofing, Veneer:
9/1 -
Area C, Art room north foundation.
9/1
- Area E, Roofing over kitchen and mechanical electrical room.
9/2 -
Area A, Admin, concrete slab on grade placement.
9/2
- Area A, Cafeteria, Barrel joist erection.
9/3
- Area C and D, CMU bearing walls.
9/8
- Area A, Cafeteria, Brick veneer.
9/9 - Area A,
Admin, Barrel joist erection.
9/9 - Area C,
Art room concrete slab on grade placement.
9/9 -
Area B, Lightweight truss erection.
9/14
- Area A, Admin, Barrel joist erection.
9/15
- Area A, Gymnasium, Roof crickets.
9/18
- Area A, Admin, metal decking.
9/24 -
Area D, lightweight truss erection.
9/30
- Area A flat roof section north of mechanical mezzanine and south of
gymnasium, viewing west.
9/30
- Area A flat roof section over stage.
Interior Construction:
9/10
Area C Mezzanine, Elevated deck concrete placement.
9/11
- Metal studs at Area A, Admin Mezzanine.
9/29
- Area A, Admin, metal stud framing.
Systems:
9/14
- Area A Admin, Electrical conduit rough in.
9/14
- Transformer and generator pads.
9/16 - Area
B Mezzanine, water source heat pumps.
Sitework:
Pumpstation:
9/8 -
Subgrade.
9/9 -
Base.
9/11
- Antiflotation Collar.
9/14
- Antiflotation Collar.
9/18 -
Backfilling.
9/11
- Entrance road, aggregate base.
9/29
- Turnlane in median serving Rte 460W.
The following includes work performed during August:
· Sitework operations continued. Installed sanitary sewer, water lines, and grading.
· Began excavation for the sewer force main pump station.
· Began road bed construction for access road.
· Continued concrete construction. Progressed foundations and slab work.
· Continued masonry construction.
· Continued roof framing and structural steel erection.
· Continued metal roof decking.
· Continued sprinkler installation.
· Continued mechanical, electrical and plumbing rough ins.
Photos:
Roof System - Structural Steel, Trusses, Decking:
8/3
Area B east wing porch.
8/4 Area B
roof trusses.
8/6
Area B, from left to right: west wing, central and east wing.
8/17 Area
A media center.
8/24 Area B
roof decking.
8/27
Area A flat roof.
8/27 Area
A media center.
8/27 Site
overview. Viewing SW. Area B in foreground.
Concrete & Masonry:
8/4
CMU walls in corridor 32, Area A.
8/4
Finishing cafeteria slab, Area A.
8/17
South cafeteria wall masonry operations, Area A.
8/25
South cafeteria wall masonry, Area A.
Systems:
8/5
HVAC pumps in Mechanical/Electrical room, Area E.
8/27
Ductwork installation, Area B.
The following includes work performed up to July 31:
· Site grading operations continued. Grading the bus loop road and the west building pad in Areas C and D. Began distributing topsoil at the soccer field.
· Continued placing waterlines.
· Completed the sewer force main between Crozier Road and the pump station site.
· Continued storm drainage structures.
· Began excavating for the bioretention area.
· Continued concrete foundations. Worked in Area C.
· Continued constructing masonry foundation walls. Worked in Areas C and D.
· Continued concrete slab construction. Worked in Areas A (batch 2) C, D.
· Continued constructing masonry walls. Worked in Areas A (batches 2, 3 and 4), B, and E.
· Continued roof framing in Area E.
· Began placing barrel joists/roof framing in Area A (batch 4 media room).
· Began placing metal roof decking in Areas A (batch 3) and E.
· Began placing brick ledges for Area A (batches 2 and 3) for the exterior walls of the cafeteria and gymnasium.
· Began framing the mechanical room decks in Area B.
· Continued under slab electrical and plumbing rough ins in Areas A (batches 2 and 4), C and D.
· Continued in wall plumbing and electrical rough ins in Areas B and C. Surface mounting electrical rough in in Area E.
· Began overhead rough in of mechanical ductwork and HVAC piping in Area E.
Photos:
Concrete Foundations & Slabs
Area
C (7/7/09).
Area D
(7/16/09).
Area A
cafeteria slab prepared (7/29/09).
Area
A media slab concrete placed (7/31/09).
Masonry
Area
A Stage (7/6/09). Area
A Cafeteria, Viewing from the parent drop off (7/13/09).
Area
B corridor interior masonry (7/22/09).
Area
A admin area masonry construction (7/23/09).
Area
A gymnasium damp-proofing (7/30/09).
Area
B interior masonry at mezzanine (7/30/09).
Steel
Roof
decking Area E (7/10/09).
Area
E decked (7/13/09).
Erecting
Area A media room barrel joists (7/14/09).
Area
A media room barrel joists (7/22/09).
Area
A gym roof decking (7/23/09).
Area B
mezzanine framing and decking (7/28/09).
Systems
Ductwork
has arrived (7/16/09).
Area E
ductwork (7/21/09).
Area
A media room underslab electrical rough in (7/22/09).
Area
E HVAC piping (7/23/09).
Area
E mechanical pumps (7/28/09).
Area
E fire suppression riser (7/30/09).
Site work
Distributing
topsoil for the soccer field (7/23/09).
Waterline
construction (7/28/09).
The following includes work performed during weeks ending May 29 and July 3:
· Site grading operations continued. Grading the access road. Began water main installation. Began gravity sewer and continued sewer force main. Continued storm drainage. Extending the building pad fill in Area C and D.
· Continued concrete building foundations, working in Area A batches 2, 3 and 4, and Area B. Began foundation work for Area C and Area D.
· Continued concrete slab construction, working in Area A batches 2 and 3, Area B and Area E
· Constructing concrete stage walls and slab, Area A batch 2.
· Continued masonry foundations, Area A batches 2 and 4, and Area B. Began masonry foundations in Area C and D.
· Continued masonry wall construction, working in Area E, Area A batches 2, 3, and 4, and Area B walls.
· Set door frames as needed.
· Began installing structural steel members in Area E, Area A batches 2, 3 and 4, and Area B.
· Continued underground electrical and plumbing rough ins.
· Began installing sprinkler supply mains.
· Continued electrical wall rough ins.
Photos:
Foundations & Slab Prep
6/2
- Area B stone and vapor barrier & Underground kitchen rough ins
6/3
- Area B north wing concrete slab finishing.
6/22 -
Foundations reinforcing.
6/24
- Kitchen concrete slab finishing

6/30
- Area A batch 2 stage slab prepped. 7/1 - Finishing slab.
7/1 - Area D
masonry foundations. Gym slab finishing.
Masonry: Gym Walls on 5/29, Area B end wall on 6/22, Area B core on 6/22,
Area A on 6/30
Steel Erection: Area E on 5/26, Area A batch 3 on 6/22, Area A batch 2 on
6/22, and Area B on 6/30
Grading: Access Road on 6/2 and 6/22. Site Drainage on 6/9.
· Site grading operations continued. Grading the bus loop and access road. Continued sewer force main. Jack and bored under Crozier Road for force main. Installed storm drainage.
· Continued concrete building foundations. Working on loading dock. Placed first concrete slab section.
· Continued masonry foundations and walls.
· Continued setting door frames.
· Continued underground electrical and plumbing rough ins. Continued electrical wall rough ins.
Photos:
Area E Masonry Walls. May 8. May 19.
Loading dock formwork. May 12.
Concrete slab work in Area B. Vapor Barrier on May 19. Placement and Finishing on May 21.
· Site grading operations continued. Preparing the west end of the building pad (completed) and grading the bus loop. Continued sewer force main. Jack and bored under Barnett Road for force main. Installed storm drainage.
· Continued concrete building foundations.
· Continued masonry foundation walls. Began masonry walls.
· Began setting door frames.
· Continued underground electrical and plumbing rough ins. Began electrical wall rough ins.
Photos:
Masonry Operations. Foundations on April 9. April 24 (2 pictures). Kitchen Wall April 28.
Underground Rough Ins. April 10. April 16 (Kitchen).
Jack and Bore for Sewer Force Main. April 28.
· Branch continued site grading operations. Continued stripping topsoil, grading and preparing the building pad. Shifted grading operations from east end of the building pad to the west end and the bus loop. Began installing the sewer force main. Began backfilling the box culvert.
· Began excavation and placed concrete for building foundations.
· Began CMU operations.
· Began electrical and plumbing underground rough ins.
Photos:
Foundation operations. March 9. March 11. March 12.
Box culvert. March 2. March 10.
· Branch continued site grading operations and excavation of the storm water management basins. Continued stripping topsoil for the building pad and concentrated grading operations on the eastern portions of the building pad. Continued operations for outlet pipes for the storm water management basins. Began installing the box culvert.
· During the last week of February, the first section of building pad was proof rolled.
· Project sign was installed.
· Commissioning kickoff meeting was held on February 18.
Photos:
Building Pad. Proof rolling. Grading. February 25.
Temporary seeding. February 25.
Box Culvert installation. February 18, February 20, February 25.
Project sign installed. February 16.
Anti-seep collar and storm water management structure. February 6.
· Branch began installing outlet pipes for storm water management basins #1 and #2. Grading operations were continued and construction fences were installed.
Photos:
Outlet pipe for storm water management basin #2. January 16:
Fill area between building pad and storm water management basin #1. January 5:
· Montgomery County Public Schools issued the Notice to Proceed on Monday, December 1.
· Groundbreaking ceremony was held on December 9.
· Preconstruction conference was held on December 10.
· Branch received and began connections for the job site office trailers.
· Branch installed siltation controls, began clearing operations and began excavating for the storm water management basins. Fill operations for the bus loop road and the topsoil stockpiles were started.
Photos:
Access road cleared. December 23:
Groundbreaking ceremony held on December 9: